At HSLIC, we believe everyone deserves access to technology that supports their learning - whether they’re preparing for exams, participating in telehealth simulations, or conducting research to advance health equity in New Mexico and beyond.

That’s why we launched the Telecommunications Room (TR) Integration & Upgrade Project — a three-phase infrastructure improvement plan that directly addresses longstanding concerns about network reliability and internet access throughout our library building.

We’re excited to report that we’re nearing the finish line: Phase 2 is wrapping up now, and completion of Phase 3 is expected within the next 30 days.


Why This Matters 

The original network infrastructure at HSLIC was designed in the 1990s to serve "approximately one device for every three students." This base network structure has been upgraded repeatedly over the years, but no longer meets the needs of our learners. Most of our students, faculty, and staff rely on at least three devices at any given time: a laptop, smartphone, and a tablet or smartwatch—often all running simultaneously during high-stakes academic or clinical activities.

By the end of this project, our building will support:

  • Faster, more reliable WiFi on the 3rd and 4th floors

  • New TR rooms on every upper floor with updated switchboards

  • Future-ready CAT-6e and fiber-optic infrastructure built for scale

These upgrades mean fewer dropped connections during exams, smoother streaming for telehealth modules, and dependable access for all — whether you’re booking a group study room or accessing essential clinical databases from a quiet pod.


Prioritizing Accessibility and Equity

As part of HSLIC’s commitment to justice, equity, and inclusion, this project is about more than just bandwidth. It’s about equal access to the resources every learner needs to succeed. Improved network infrastructure reduces digital disparities and helps ensure that all UNM Health Sciences Center students—regardless of discipline, background, or device—can fully participate in their education without barriers.

From our privacy-focused study pods to ADA-compliant upgrades, these improvements support an inclusive, accessible, and affirming library experience for everyone.


What to Expect During Final Construction

Phase 3 construction on the 4th floor is now underway and expected to be completed by the end of July. You may notice:

  • Intermittent construction noise during daytime hours

  • Limited access to some seating zones or adjacent rooms

  • Temporary signage and rerouted foot traffic

We are doing everything possible to minimize disruptions and maintain access to study rooms and services during this time. If you have questions about quiet spaces, accessibility, or internet performance during this final phase, please connect with our Service Desk staff or reach out via Ask a Librarian.


What’s Next

Once all work is complete, we’ll move into the final testing and configuration phase. You can expect:

  • Even distribution of high-speed WiFi across all floors

  • A seamless connection experience in all group and solo study spaces

  • Infrastructure designed to support future innovation and growth

We’ll continue to share updates as we move toward completion. Until then, we thank you for your patience—and we’re honored to continue investing in the digital infrastructure that supports your academic journey.